|
BACK
Article published Aug 23, 2006 in the Royal Gazette
Burch: Firm could not meet obligations
By Elizabeth Roberts
A Canadian engineering firm that had been canvassing opinion on a new
crossing for Castle Harbour had its contract terminated because it could
not meet obligations, Government said yesterday.
Works and Engineering Minister David Burch said of the split with Associated
Engineering, which was jointly awarded the contract with OBM International: "They
got too much business. The bottom line was that this was a small project
for them and they weren't really able to get started.
"The separation has been amicable and we have reached a settlement
with them."
Outlining how the project to replace the Causeway which was damaged
in Hurricane Fabian will now progress, the Minister said the total budgeted
cost for the feasibility study was now $1,506,000 – around $600,000
more than originally anticipated. He explained this was mainly due to
an expansion in the scope of geotechnical and environmental studies and
in public consultation.
"As the final solution to the Causeway is likely to cost in the
tens of millions of dollars this investment will result in a more detailed
feasibility study, thereby reducing some of the unknowns during the design
stage of the project," he said.
Among the options being examined besides rebuilding or upgrading the
existing Causeway are a tunnel or even a new bridge across Coney Island,
said Sen. Burch, who stressed there were no preconceived ideas on the
preferred option.
He said that after the termination of the contract with the Associated
Engineering consultants, it was deemed to be most cost effective to contract
directly with sub consulting groups in future and expand the role of expert
Ministry staff.
The next phase of the feasibility study will see Aardvark Drilling Inc
of Guelph, Ontario, commence drilling and sampling in the waters of Grotto
Bay to determine the strength of the underlying rock. This work will start
early next month.
The public consultation phase of the project will begin concurrently
with this, said the Minister. This will see stakeholders including local
businesses and environmental groups contributing their interests and concerns.
Local firm OBM will manage this part of the project and open meetings
will be held in Hamilton and St. George this autumn. The public will have
the opportunity to review the material collected to date as well as participate
in a survey designed to engage the public in the planning process.
"All data collected will be analysed and presented at further public
meetings scheduled for the new year," added the Minister.
The study is due to be completed in spring 2007. Explaining how the
increased cost will be met, Sen. Burch said that Bank of Bermuda HSBC
had committed $250,000 and the balance is included in the Ministry's 2006/07
budget.
"The cost of a causeway is likely to be sizeable and the Ministry
is currently engaged in exploring alternative financing options," he
said, explaining that a "guesstimate" for the whole project
at this stage is in the $60 million mark but likely to rise.
Asked whether he anticipated seeking assistance from Britain, he responded: "Well,
we are a colony so we will have to ask, but they have not given us much
money in the last 450 years so they're unlikely to start now."
BACK
|